Adani Energy Solutions has won a major Bihar transmission project to evacuate power from the upcoming 2,400 MW Pirpainti power plant. The project, expected to be completed by Q4 2028, will generate an annual tariff of around Rs 500 crore and strengthen Bihar's power network.

  • Facebook Share Icon
  • Twitter Share Icon
  • WhatsApp Share Icon
 
Follow : Google News Icon
Adani Energy Wins Rs 500 Crore Bihar Power Transmission Project
Adani Energy Wins Rs 500 Crore Bihar Power Transmission Project | Image: Republic Initiative

Ahmedabad: Adani Energy Solutions Limited (AESL), India’s leading private sector power transmission and distribution company, today said it has won a transmission project for evacuation of power from the upcoming 2400 MW power plant in Pirpainti, Bihar. The project, won through the Tariff Based Competitive Bidding (TBCB) mechanism, will provide annual tariff of Rs ~Rs 500 cr once commissioned. 

The project, titled, “Evacuation of Power from 3X800 MW STPP Pirpainti”, will be implemented through the Special Purpose Vehicle (SPV) Vikramshila Power Transmission Ltd. and will be delivered by the last quarter of 2028. Besides evacuation of power from the Pirpainti Power Plant, the project will strengthen the state’s transmission network and enhance supply reliability.

“The Pirpainti transmission scheme will create a robust evacuation system for 2,400 MW of generation capacity while strengthening Bihar’s transmission backbone. It will enhance grid reliability and resilience and help the state meet its growing power demand. We remain committed to building reliable and efficient transmission infrastructure that supports the country’s long-term energy security,” said Mr. Kandarp Patel, CEO, Adani Energy Solutions. 

Upon completion, the project will add 881 circuit kilometres (ckm) of transmission lines and 3,160 MVA of transformation capacity to AESL’s portfolio, taking it to 30,683 ckm and 146,585 MVA. With this project, AESL’s transmission capex now stands at ~Rs 91,500 crore. 

Advertisement

The project comprises construction of four Gas Insulated Substations (GIS) at Jhanjharpur, Bethauli and Begusarai, along with associated transformation capacity. The transmission infrastructure will include the 400 kV DCDS Pirpainti-Jhanjharpur, Pirpainti-Begusarai and Begusarai-Bakhtiyarpur lines, as well as the 220 kV DCDS Jhanjharpur-Bethauli and Begusarai-Begusarai Town lines. It will also involve LILO of existing 220 kV and 132 kV transmission lines at Jhanjharpur and construction of 400 kV line bays at Bakhtiyarpur GSS.
 